How to Bid With No Past Performance

No government contracts yet? How the FAR treats firms without past performance, what experience counts, and practical ways to build a record from scratch.

You can win government contracts without past performance. Under FAR 15.305, an offeror with no relevant record “may not be evaluated favorably or unfavorably” on past performance, and agencies must let you cite similar commercial, state and local work. You can also rely on the experience of your key people and major subcontractors, team with an experienced partner, or start with smaller and subcontract work to build a record.

“Past performance” sounds like a wall for new government contractors. It’s more of a hurdle, and the rules are friendlier than most people assume. This guide explains how evaluators treat new firms and how to build a record.

Key takeaways

  • No record means a neutral rating, not a failing one, under FAR 15.305(a)(2)(iv).
  • Commercial, state and local work counts if it’s similar to the requirement.
  • Key personnel, predecessor companies and major subcontractors can supply relevant experience.
  • Lack of history alone can’t make you nonresponsible under FAR 9.104-1.
  • Subcontracting, teaming and smaller awards are the fastest ways to build a federal record.

How do agencies evaluate firms with no past performance?

For negotiated procurements, FAR 15.305 sets the rules:

  • Past performance is “one indicator” of ability to perform. Agencies consider how recent and relevant it is, its source and context, and general trends.
  • The solicitation must describe how the agency will evaluate offerors with no relevant performance history.
  • If you have no record of relevant past performance, or the information isn’t available, you may not be evaluated favorably or unfavorably on past performance. That’s often called a neutral rating.

A neutral rating won’t beat a strong, relevant record in a best-value tradeoff. But it doesn’t disqualify you, and on lowest price technically acceptable (LPTA) buys, where award goes to the lowest-priced acceptable offer, it may matter less. Under FAR 15.101-2, past performance doesn’t even have to be an evaluation factor in an LPTA procurement if the contracting officer documents why.

What experience counts as past performance?

More than you might think. FAR 15.305(a)(2)(ii) says solicitations must let offerors identify past or current contracts, including federal, state, local government and private, for efforts similar to the requirement. The source selection authority decides how relevant each one is.

So a janitorial company that cleans three large private office campuses has relevant experience for a federal office building. An IT firm that supports a hospital network has relevant experience for an agency help desk. What matters is similarity in scope, size and complexity.

Can I use my team’s experience?

Yes, when it’s relevant. FAR 15.305(a)(2)(iii) says the evaluation should take into account past performance of:

  • Predecessor companies
  • Key personnel who have relevant experience
  • Subcontractors that will perform major or critical aspects of the work

If your founder ran federal facility contracts for a large prime before starting your company, that experience can support your proposal. Describe it specifically, with roles, scope and dates, and follow any instructions in the solicitation about how to present it.

For joint ventures, FAR 15.305(a)(2)(vi) says that if the joint venture itself doesn’t show past performance, the contracting officer must consider the past performance of each party.

Can an agency refuse to award to me because I’m new?

Not for that reason alone. Before award, the contracting officer must decide whether you’re responsible, meaning able to perform. Under FAR 9.104-1(c), a prospective contractor can’t be determined responsible or nonresponsible solely on the basis of a lack of relevant performance history, except in limited cases.

There’s another safeguard for small businesses. Under FAR 19.601, if a contracting officer finds an apparently successful small business offeror nonresponsible, the contracting officer must refer it to SBA for a possible Certificate of Competency, which certifies the business as responsible for that contract.

How do I build past performance from scratch?

1. Write up your commercial work properly

Pick three to five projects most similar to the government work you want. For each, record the customer, scope, contract value, dates, staffing, results and a reference who will take a call. You’ll reuse these in every proposal and in your capability statement.

2. Start with smaller buys

Purchases up to the simplified acquisition threshold, now $350,000, are generally set aside for small businesses and use simpler procedures. Smaller awards are a practical place to start. See micro-purchase and simplified acquisition thresholds.

3. Subcontract to a prime

Large primes on contracts over $900,000 ($2 million for construction) with subcontracting possibilities generally must submit small business subcontracting plans under FAR 19.702, so many actively look for small partners. SBA’s SUBNet lists subcontracting opportunities. Subcontract work gives you relevant experience and references you can cite later.

4. Team or form a joint venture

Partnering with an experienced firm lets you bid work you couldn’t win alone. The SBA Mentor-Protégé program lets a mentor and protégé joint venture as a small business for any small business contract, provided the protégé individually qualifies as small.

5. Work state and local contracts

State and local work is government past performance, and it’s often closer to home. See how to find state and local government contracts.

6. Earn good evaluations

Once you’re performing federal work, agencies record evaluations in the Contractor Performance Assessment Reporting System (CPARS). Communicate early, document your work, and fix problems fast. Your first evaluations shape your record for years.

How should I write the past performance section?

  • Follow the instructions exactly. If the solicitation asks for three references on a specific form, give three on that form.
  • Lead with relevance. Say in the first line why each project is similar: scope, size, complexity, environment.
  • Use numbers. Square footage, sites, users, response times, contract value, staff.
  • Be honest about problems. FAR 15.305 lets you describe problems and the corrective actions you took. A handled problem can show reliability.
  • Brief your references. Tell them the agency may call and what the project was.

For where to find primes and how to approach them, see how to find subcontracting work with federal primes.

Where Bidstream fits

Bidstream looks at all four routes in, not just bidding as the prime: subcontracting to a larger prime, teaming with another small business, and supplying the company that already won. For a company building its record, those routes are often the best start. Sign up and Bidstream will look for the ones that fit you.

Frequently asked questions

Can I win a government contract with no past performance?

Yes, it's possible. Under FAR 15.305, an offeror without a record of relevant past performance may not be evaluated favorably or unfavorably on past performance. Some evaluation methods, such as lowest price technically acceptable, award to the lowest-priced acceptable offer.

Does commercial work count as past performance?

It can. FAR 15.305 says solicitations must give offerors the chance to identify past or current contracts, including federal, state, local and private ones, for efforts similar to the government's requirement. The agency decides how relevant each is.

Can I use my employees' experience as past performance?

Often, yes. FAR 15.305 says the evaluation should consider past performance of predecessor companies, key personnel with relevant experience, or subcontractors that will perform major or critical parts of the work, when relevant.

Can an agency reject me just because I'm new?

Not on that basis alone. FAR 9.104-1 says a prospective contractor can't be found responsible or nonresponsible solely because it lacks relevant performance history, except in limited cases. If a small business is found nonresponsible, the contracting officer generally must refer it to SBA for a possible Certificate of Competency.

What is CPARS?

The Contractor Performance Assessment Reporting System is where federal agencies record evaluations of contractor performance. Once you complete federal work, those evaluations become part of the past performance record that future buyers can review.