Micro-Purchase Threshold and SAT, Explained
Since October 1, 2025, the federal micro-purchase threshold is $15,000 and the simplified acquisition threshold is $350,000. What each means for you.
Since October 1, 2025, the federal micro-purchase threshold is $15,000 (up from $10,000) and the simplified acquisition threshold is $350,000 (up from $250,000). Purchases at or below $15,000 can usually be made with a government purchase card without competitive quotes, and purchases above that up to $350,000 are generally set aside for small businesses and bought with simplified procedures.
These two numbers shape how agencies buy, how much paperwork they need, and which contracts are reserved for small businesses. Here’s what they are now, what changed, and how to use them.
Key takeaways
- Micro-purchase threshold (MPT): $15,000, or $2,000 for Davis-Bacon construction and $2,500 for Service Contract Act services.
- Simplified acquisition threshold (SAT): $350,000.
- Both rose on October 1, 2025 in the FAR Council’s inflation adjustment (90 FR 41872).
- Work between the MPT and SAT is generally set aside for small businesses.
- Bond thresholds, Davis-Bacon and Service Contract Act thresholds were not adjusted.
What is the micro-purchase threshold?
The micro-purchase threshold is the dollar level below which agencies can buy with the least paperwork. FAR 2.101 defines it as $15,000, with exceptions:
- $2,000 for construction subject to the Davis-Bacon wage requirements
- $2,500 for services subject to the Service Contract Labor Standards statute
- $25,000 inside the U.S. and $40,000 outside it for some contingency, emergency and defense-related purchases
Under FAR 13.201, the government purchase card is the preferred method for micro-purchases. Under FAR 13.203, micro-purchases may be awarded without competitive quotes if the buyer considers the price reasonable, and should be spread equitably among qualified suppliers where practicable.
What does the micro-purchase threshold mean for my business?
It means a lot of small federal buying never shows up as a posted solicitation. A facility manager who needs a $9,000 repair can call a local company, confirm the price is reasonable and pay by card.
To be the company they call:
- Accept credit cards. Purchase cards are the preferred payment method.
- Know the local buyers. Introduce yourself to facility managers and contracting offices at federal sites near you.
- Price transparently. Buyers need to judge your price as reasonable.
- Watch the exceptions. For construction under Davis-Bacon, the threshold is only $2,000, and for covered services it’s $2,500, so most trade jobs above those amounts follow fuller procedures.
FAR 4.1102 exempts micro-purchases made with a purchase card used for both buying and payment from the SAM registration requirement. Larger work still needs an active SAM.gov registration.
What is the simplified acquisition threshold?
The simplified acquisition threshold, defined in FAR 2.101, is $350,000. Below it, agencies can use simplified acquisition procedures under FAR Part 13, such as requests for quotations, with less formal evaluation and documentation than a full FAR Part 15 source selection. Higher thresholds ($1 million inside the U.S., $2 million outside it, and $650,000 for some humanitarian operations) apply to certain contingency, emergency and humanitarian buys.
Why does the SAT matter to small businesses?
Because of set-asides. Under FAR 19.502-2, each acquisition of supplies or services above the micro-purchase threshold and up to the SAT is set aside for small business unless the contracting officer doesn’t expect offers from two or more responsible small businesses competitive on price, quality and delivery. If only one acceptable small business offer arrives, the contracting officer should award to that firm.
In plain terms: between $15,000 and $350,000, the default is that small businesses compete only against each other. Above $350,000, the same “rule of two” test applies, but it’s applied case by case. To check whether you count as small, see SBA size standards.
The FAR is being rewritten under the Revolutionary FAR Overhaul. The proposed Part 19 text keeps the rule of two for acquisitions above the micro-purchase threshold, but section numbers differ. Follow the language in each solicitation.
What other thresholds changed on October 1, 2025?
The same rule adjusted dozens of thresholds. These are the ones service companies run into most, from Acquisition.gov’s threshold table:
| Threshold | Before | Since Oct 1, 2025 |
|---|---|---|
| Micro-purchase threshold | $10,000 | $15,000 |
| Simplified acquisition threshold | $250,000 | $350,000 |
| Public display of proposed contract actions | $15,000 | $20,000 |
| First-tier subcontract reporting | $30,000 | $40,000 |
| Small business subcontracting plan (prime contracts) | $750,000 | $900,000 |
| Small business subcontracting plan (construction) | $1.5 million | $2 million |
| 8(a), HUBZone and WOSB sole source (non-manufacturing) | $4.5 million | $5.5 million |
| SDVOSB sole source (non-manufacturing) | $4 million | $5 million |
| Sole source for any of these (manufacturing) | $7 million | $8.5 million |
| Simplified procedures for commercial products and services | $7.5 million | $9 million |
The subcontracting plan thresholds matter if you want to work under larger primes: above $900,000 ($2 million for construction), a large business prime with subcontracting possibilities generally must submit a small business subcontracting plan under FAR 19.702. That’s a big reason primes look for small partners.
The requirement to synopsize contract actions on SAM.gov still starts above $25,000 under FAR 5.101. See how to find federal contracts on SAM.gov.
Which thresholds did not change?
The law behind the adjustment, 41 U.S.C. 1908, excludes some thresholds. According to the final rule, these were not adjusted:
- The Davis-Bacon (Construction Wage Rate Requirements) thresholds
- The Service Contract Labor Standards thresholds
- Performance and payment bond thresholds
- Trade agreements thresholds
So under FAR 28.102-1, federal construction contracts over $150,000 still require performance and payment bonds, and construction contracts over $35,000 up to $150,000 still require payment protection chosen by the contracting officer.
When will the thresholds change again?
The statute requires an adjustment every five years, on October 1 of years evenly divisible by five. The next scheduled adjustment is October 1, 2030. Thresholds can also change through separate legislation or rulemaking.
How should I use these numbers?
- Target the small business reserve. Opportunities between $15,000 and $350,000 are set aside for small businesses by default, so you compete against companies your size.
- Make micro-purchases easy. Take cards, publish clear prices, and get known at local federal facilities.
- Track subcontracting-plan primes. Large awards over $900,000 create demand for small partners.
- Price construction with bonding in mind. Above $150,000, plan for bonds. Above $2,000, plan for Davis-Bacon wages.
Where Bidstream fits
Bidstream watches the whole range, from smaller posted buys to large awards where primes need partners, and matches them to your trade, size and location. Sign up to get matched opportunities by email.
Frequently asked questions
What is the federal micro-purchase threshold in 2026?
$15,000 for most purchases, effective October 1, 2025. It is $2,000 for construction subject to the Davis-Bacon wage requirements and $2,500 for services subject to the Service Contract Labor Standards statute.
What is the simplified acquisition threshold in 2026?
$350,000, effective October 1, 2025, up from $250,000. Higher amounts apply to some contingency, emergency and humanitarian purchases.
How often do federal acquisition thresholds change?
Statutory thresholds are adjusted for inflation every five years, on October 1 of years divisible by five. The last adjustment took effect October 1, 2025, so the next scheduled one is October 1, 2030.
Do micro-purchases have to be competed?
No. Under FAR 13.203, micro-purchases may be awarded without competitive quotations if the buyer considers the price reasonable, and they should be distributed equitably among qualified suppliers to the extent practicable.
Are contracts under the simplified acquisition threshold set aside for small businesses?
Generally, yes. Under FAR 19.502-2, purchases above the micro-purchase threshold and up to the simplified acquisition threshold are set aside for small business unless the contracting officer doesn't expect offers from two or more responsible small businesses at fair market prices.
Did the bond threshold change in 2025?
No. Performance and payment bond thresholds were excluded from the inflation adjustment. Federal construction contracts over $150,000 still require performance and payment bonds.